Sheek Road truck signage
The council banned semi-truck traffic on Sheek Road after years of resident complaints. Campbell warned trucks may now be cutting through Bainbridge and other nearby streets, so this problem may resurface.
Main Street Segments 3 & 4 Right-of-Way Settlements
Main Street between Meridian and Polk Streets will be rebuilt, with the waterline replaced this year and full roadway work starting in early 2027 — expect bid ads in June and a possible award July 6.
Motorized scooter and e-bike regulations
Resident David Johnson told the board that motorized bicycles, gas bikes and scooters — some running after dark with no lights — are increasingly common on park trails, and someone will eventually get hurt. Staff and board members agreed it's a growing problem but said the department has no enforcement power; the only recourse is calling the police. Existing signs prohibit motorized vehicles, but rules haven't been updated for the explosion of battery-powered bikes.
Arbor Homes $40,000 intersection donation
Because Scottsdale Estates East sits close to the Honey Creek/Whiteland Road intersection, Arbor Homes is paying $40,000 toward the intersection's traffic impact, formalized in a donation agreement.
Smith Valley Road Segment 3 federal funding
The Smith Valley/Averitt roundabout needed $24,102 more in asphalt to get proper drainage and slope — but the city says the whole project should still finish under its original contract price.
Averitt Road sidewalk gaps
Duke Energy is replacing transmission poles and wire along Worthsville Road and Collins Road through April 2026, which means intermittent 10-minute road closures (mostly overnight) and daytime lane restrictions. Drivers through that corridor — including near Clark-Pleasant Middle School — should expect occasional delays.
Smith Valley Road widening funded 80%
The city landed roughly $8.4 million in federal MPO money toward the $10.6 million widening over the railroad tracks, and hired Lochmueller for design — bidding late 2028, construction 2029. The county bridge replacement upstream is on its own track for 2027-28.
Trail projects headed to bid in 2027
The long-delayed AES trail could finally go out to bid in March 2027 — board members noted it's been in the works for seven years. Cherry Tree Walk, Westwood, and the Summerfield/Westside and Sports Park bridges are also moving through permitting, easements and bidding.
Main Street Segments 3 & 4 right-of-way acquisition
The corridor project between Meridian Street and just east of 12th Street is acquiring right-of-way, aiming to start construction in 2026; a $15,200 amendment covers negotiation work to avoid condemning properties and Duke Energy relocation coordination.
Main Street eastbound lane closure for water main replacement
Three Old Town streets will close weekdays from April 20 to May 1 while Indiana American Water cuts and caps an aging main. Residents keep access, but drivers should expect detours through Greenwood Street.
Pedestrian safety on Stop 18 Road
The RDC approved $14,980 for pedestrian-activated flashing crossing signals on Stop 18 Road near the Thornton's gas station, connecting sidewalks and the trail on both sides. The Street Department will install and maintain them.
Griffith Road Closure and Reconstruction
Emerson Avenue between Pushville and Tracy roads will fully close for 35 days starting July 27 while Lennar completely rebuilds and widens the roadway. It's a popular route, and the closure is tied to the railroad's separate Worthsville Road work, which is the detour route.
Whiteland/Honey Creek intersection improvements and future roundabout
The city is moving ahead with a roundabout at the offset intersection of Honey Creek, Smokey Row and Tracy Roads. VS Engineering will handle design and bidding help for $459,000, with bids hoped for late 2027 and construction in 2028, all paid with local funds.
Traffic study timing debate
One remonstrator asked the commission to defer action until the traffic study was complete, warning taxpayers could get stuck widening Honey Creek later. Staff explained the developer won't fund engineering studies before it knows the zoning is approved, so the study was made a binding commitment instead.
2026 Paving Project Expansion – Grassy Creek Lane
The board authorized bidding for the 2026 paving program; final street list isn't set yet, with award expected in March.
Worthsville Road Railroad Crossing Delayed
The Louisville & Indiana Railroad offered a tiny July 21–23 closure window for the crossing work, which the city's paving contractor couldn't commit to. The work won't happen this year, and future attempts may require a costly railroad permitting process — with the closure starting the day after the meeting.
Westwood Trail land acquisition
Cherry Tree Walk remains stuck in design development, but Westwood Trail appraisals are done and the city will soon make purchase offers to property owners for the small connector trail.
Railroad Crossing Roadwork Contract Dispute
The city's deal with Legacy Excavating to mill and overlay roads by the railroad tracks fell apart over a warranty dispute — the contractor offered only a 60-day warranty. The city is now seeking a quote from Howard Companies.
Bridge-over-nothing dispute: Alexander Ditch crossing commitment
Staff wants the developer to build one of two bridges over Alexander Ditch to set up a future collector road connecting Honey Creek Road to County Road 75. The developer calls it a $500,000-to-$1 million 'bridge to nowhere' that could sit unused for 20 years — and the commission sent the commitment on as written anyway. Expect negotiation at the Council level.
Smith Valley Road/Woodmen Boulevard Roundabout Completion
The roundabout, open to traffic since November 6, 2025, is formally closed out with a final change order that brought the project about $65,700 under the original contract — a 4.11% savings.