Smith Valley Road/Woodmen Boulevard Roundabout Completion
Summary
The roundabout, open to traffic since November 6, 2025, is formally closed out with a final change order that brought the project about $65,700 under the original contract — a 4.11% savings.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Jun 1, 2026.
Impact analysis
The project ended about $65,700 cheaper than contracted.
Everyone who drives the Smith Valley/Woodmen intersection gets a finished roundabout at a lower cost to the city.
Mentions & discussions (2)
Board of Public Works — June 1, 2026
The roundabout, open to traffic since November 6, 2025, is formally closed out with a final change order that brought the project about $65,700 under the original contract — a 4.11% savings.
Board of Public Works — March 2, 2026
The roundabout is substantially complete with only minor spring work left. The final change order covered Duke Energy-required power for lighting and delivered a net $63,004 deduction — roughly 4% under the original contract.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Greenwood
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.