Smith Valley Road Segment 3 federal funding
Summary
The Smith Valley/Averitt roundabout needed $24,102 more in asphalt to get proper drainage and slope — but the city says the whole project should still finish under its original contract price.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Sep 9, 2026.
Impact analysis
Adds $24,102 to the roundabout contract, though the total is still expected to come in under budget.
Motorists using the roundabout get proper drainage and a smoother, safer surface.
None identified.
Mentions & discussions (2)
Common Council — September 9, 2026
The city wants federal money to extend Smith Valley Road from Valley Oaks Road to Emerson Avenue, and the council's signed support letter will be part of the application due September 30. It's an east-side congestion and connectivity fix.
Board of Public Works and Safety — April 20, 2026
The Smith Valley/Averitt roundabout needed $24,102 more in asphalt to get proper drainage and slope — but the city says the whole project should still finish under its original contract price.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Greenwood
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.