Main Street Segments 3 & 4 Right-of-Way Settlements
Summary
Main Street between Meridian and Polk Streets will be rebuilt, with the waterline replaced this year and full roadway work starting in early 2027 — expect bid ads in June and a possible award July 6.
At a glance
- Total mentions
- 3
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 4, 2026.
Impact analysis
Total project cost not yet known; bids open June 25, 2026.
Drivers and residents along Main Street, plus the water company through the coordinated waterline replacement.
Drivers and businesses may face construction disruption on Main Street during 2026-2027 work.
Mentions & discussions (3)
Board of Public Works — November 4, 2026
The board approved negotiated settlements on three of about 20 parcels needed for the Main Street reconstruction, avoiding condemnation and keeping the project targeted for late 2027/early 2028. More road closures are coming when construction resumes in spring.
Board of Public Works and Safety — August 3, 2026
The city is buying small slivers of property along East Main Street for the road reconstruction between Polk Street and Vista Run. Six offer letters totaling about $51,540 were ratified to keep the project moving.
Board of Public Works — May 18, 2026
Main Street between Meridian and Polk Streets will be rebuilt, with the waterline replaced this year and full roadway work starting in early 2027 — expect bid ads in June and a possible award July 6.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Greenwood
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.