Griffith Road Closure and Reconstruction
Summary
Emerson Avenue between Pushville and Tracy roads will fully close for 35 days starting July 27 while Lennar completely rebuilds and widens the roadway. It's a popular route, and the closure is tied to the railroad's separate Worthsville Road work, which is the detour route.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Aug 3, 2026.
Impact analysis
Lennar pays a $500/day penalty for every day past the 35-day window.
Drivers and future residents get a rebuilt, widened road with acceleration/deceleration lanes, and construction workers stay safer.
Commuters who use Emerson Avenue between Worthsville and Tracy will face a 35-day detour, timed right after the railroad's closure adds its own disruption.
Mentions & discussions (2)
Board of Public Works and Safety — August 3, 2026
Griffith Road (C.R. 325 East) between Billingsly Road and Allen Road will fully close from August 24 through September 1 for full-depth reclamation under the 2026 Annual Paving Project. Local residents will keep access while the rebuilt road cures before new asphalt is laid.
Board of Public Works — June 1, 2026
Emerson Avenue between Pushville and Tracy roads will fully close for 35 days starting July 27 while Lennar completely rebuilds and widens the roadway. It's a popular route, and the closure is tied to the railroad's separate Worthsville Road work, which is the detour route.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Greenwood
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.