Smith Valley Road widening funded 80%
Summary
The city landed roughly $8.4 million in federal MPO money toward the $10.6 million widening over the railroad tracks, and hired Lochmueller for design — bidding late 2028, construction 2029. The county bridge replacement upstream is on its own track for 2027-28.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Sep 8, 2026.
Impact analysis
City share is roughly $2.2 million of the $10.6 million project.
Commuters on a major east-west corridor near the I-69 interchange.