Water and wastewater utility engineering contracts
The board was scheduled to consider several utility task orders — Donohue Task Order 19, two Peerless Mid-West task orders, and a Davis Road lift station design amendment — covering engineering work on city water and sewer infrastructure.
Davis Road lift station design
The board approved a $328,235 increase to the American Structurepoint contract to finish the Davis Road lift station design. The larger force main will likely bore under and along Brandywine Creek to avoid old dump sites at the treatment plant, with construction targeted for spring.
Waterview Lift Station relocation
A planned 49-apartment expansion near Beck Park was approved but can't proceed for about two years until the city addresses a lift station problem to the north.
Equipment Purchases and Fleet Updates
The council finalized $398,843.23 for new police vehicles and equipment for 2026, funded through the public safety portion of the local income tax.
Franklin Street Sanitary Sewer Extension Project completion
Change Order #4 would close out the Franklin Street sewer and water main project with a $113,610 reduction in contract price and release of roughly $273,000 in retainage across the water and wastewater utilities.
Water tower project payment
The board approved pay application 28 for the South Side Water Improvement Project — $389,770 including retainage — sent next to the state SRF program for review. Mayor Titus also reported a $1.6 million federal grant for lead line replacement has advanced through the House Ways and Means Committee.
Citywide sewer master plan
Commonwealth Engineers is mapping the whole city's sewer system — field work is done — to route sewage to the new west-side plant without overflows, with completion expected around September or October.
On-call engineering services consolidation
The city wants to simplify how it pays Wessler Engineering for reviewing development plans and storm sewer systems — one agreement instead of separate annual contracts, with individual task orders for each job.