The board approved pay application 28 for the South Side Water Improvement Project — $389,770 including retainage — sent next to the state SRF program for review. Mayor Titus also reported a $1.6 million federal grant for lead line replacement has advanced through the House Ways and Means Committee.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jun 9, 2026.
Impact analysis
$389,770 paid on the water tower project; a potential $1 million federal grant could offset lead line replacement costs.