Medium PriorityWater Utilitiesopen

Franklin Street Sanitary Sewer Extension Project completion

Summary

Change Order #4 would close out the Franklin Street sewer and water main project with a $113,610 reduction in contract price and release of roughly $273,000 in retainage across the water and wastewater utilities.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jun 23, 2026.

Impact analysis

💰Financial impact

The change order lowers the total contract price by $113,610 and releases $273,111.97 in combined retainage.

✅Who benefits

Ratepayers benefit from the unused contingency funds returned; areas served by the new sewer and water mains.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Greenfield

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.