Civic Issues
Topics getting the most attention in DeKalb County public meetings, ranked by how frequently they are discussed.
50 issues
2 Amigos Taqueria development plan
A development plan for a taqueria at 603 West 7th Street in Auburn was before the board, which reviews stormwater and drainage for new commercial buildings.
Replat reviews affecting Garrett and Auburn properties
Auburn's zoning change request got tabled because the application was filed wrong (it included an AI-generated site plan with comically long parking spaces). The city must hold a public hearing August 11 on its UDO and land development rules aimed at boosting housing, as Indiana law requires.
New minor subdivision near St. Joe
Three land division projects got drainage approval — new home sites in Spencerville, St. Joe, and Auburn. All checked out with the Surveyor's Office on drainage.
Mediacom utility permit agreement
Mediacom is installing fiber along CR 60 in Laotto and CR 3 in Garrett, boring under regulated drains — better internet for those areas, with the county surveyor's office marking tile locations first.
Leaf Pickup Schedule
Auburn just released its leaf pickup schedule, so if yard waste is piling up, you now know when the city is coming by. It’s a simple service update, but it saves you from guessing—or paying someone else to haul leaves away.
Public Meetings
DeKalb County has public meetings today, so you can watch local government in action or speak up on decisions that affect your community. It’s a low-effort way to see what’s being decided and make your voice heard.
Special Commission Meeting
DeKalb County commissioners are holding a special meeting, so if you care about local decisions, this is your chance to watch or speak up. The source doesn't list the agenda, but special meetings often mean time-sensitive county business. Showing up or tuning in is the easiest way to see what your elected officials are doing.
Public Meeting Notice
DeKalb County is posting its public meeting schedule so you know when to show up and have a say. If you care about local decisions, this is your heads-up. No big surprises—just a chance to get involved.
Lot splits in agricultural zones
Three property owners won approval for replats or a new one-lot subdivision in A1/A2 agricultural zones, each for single-family residences with private septic and no new public services. Growth stays low-impact — no new roads or lots beyond the splits.
Shared access and future road frontage
Landowner Michael Grimm challenged the county's long-standing practice of requiring right-of-way dedication when land is platted, calling it a de facto taking without compensation. Staff explained it's a statewide zoning-ordinance requirement dating to the early 1960s and said he's unaware of any successful legal challenge.
Tile reconstruction funding and consent-and-waiver dilemma
The board's practice of ruling on each objection letter one by one at reconstruction hearings has felt awkward. Attorney Kruse confirmed the code allows grouping similar objections, and the board will rethink its hearing agenda format.
Treesh Hills Lot 1 replat expansion
The landowner is adding acreage north of the existing lot, potentially for a new building out on County Road 34 near Kendallville. The board signed off since the surveyor's office found no drainage concerns.
Mediacom underground cable conversion in Garrett
Because the power company removed some poles, Mediacom's contractor wants to bury its cable along CR 52 in Garrett, crossing one tile drain. Standard conditions apply: hydrovac the tile and call the surveyor's office first.
Broadband permit fees vs. county drains
A 2021 state agreement bars the county from charging fees for broadband installation, but fiber is being bored across county drains all over, requiring inspector time. Staff may refund Auburn's fees and wants board direction — possibly requiring aerial lines instead.
Weights and Measures restructuring
The one-person weights and measures shop is being folded into Development Services, dropping it from a salaried department head to an hourly position under Chris Gaumer's supervision — with the budget kept separate for easy un-merging later.
Vulcraft tax abatement
Vulcraft is planning a $55 million expansion of its Saint Joe plant and requested property tax abatements. The company considered competing locations in Texas and West Virginia but prefers DeKalb County if local incentives make the financials work.
DeKalb County Regional Sewer District
The county would create an umbrella district so Auburn, Garrett and the St. Joe sewer system can qualify for grants they can't get alone — especially urgent for St. Joe, where rates top $100 a month and lift stations are failing. Two members voted no, saying they'd had too little time to study it.
Juvenile detention cost surge
A spike in juvenile detentions — several stemming from stolen weapons cases — plus a jump in Allen County's daily rate from $75 to $200 burned through the probation budget, prompting a $10,000 additional appropriation and monthly billing going forward.
DeKalb County Airport improvements
The airport logged 14,887 takeoffs and landings in 2025 — about 40 a day — and its new snow removal machine performed well. But the aging runway needs full repaving, which will close it for about six weeks this year. Hangar tenants will get rent abatements while it's shut down.
Sunny Meadows building disposal
A seven-member committee including the council's rep will recommend whether the county sells, tears down or repurposes the Sunny Meadows facility. A consultant will outline financing options that could work without cost to the county. Members debated experience versus fresh perspective for the council seat.
GIS separation from Auburn after cyber attack
Because of the September cyber incident, Auburn is cutting the county off from shared GIS hosting on December 31. The county must stand up its own system, so the council created an entry-level GIS Specialist and upgraded the administrator role — with weekend update work built in.
County Road 60 flood-prone crossing replacement
The highway department wants to fix the chronically flooding CR 60 crossing near Auburn Gear — peat up to 55 feet deep means it must be bridged on pylons, a roughly $17 million project. The county's match would be about $3.4 million, and the council must commit funds by the 2032 federal-aid call for Ben Parker to apply this November.
$51.8 Million Jail Project Financing
The jail sits above its 80-prisoner cap almost every week, and the price tag for the old plans could run $50 million at worst case — though the modular design was drawn for 240-plus beds and officials think 200 may suffice. The council wants a dedicated jail fund carved out of the rainy day fund and is weighing an income tax approach to financing to avoid a property tax referendum.
AL Ober drain relocation for NRCS waterway
Farmer Steve Grate wanted to reconstruct a non-functioning drain as part of an NRCS waterway project but couldn't get a reluctant neighbor to sign a consent form. The board found his project fits Indiana Drainage Code section 52.5 — all on his own land, surveyor-supervised, and self-funded — so no signatures were needed.
North Pointe Subdivision drain reroute and right-of-way protections
A new Auburn subdivision will reroute the Harry Shull regulated drain along the property edge as a narrower urban easement. The board added a deed/plat notice citing Indiana Drainage Code section 36-9-37-33 so future homeowners know they can't plant trees or woody vegetation on the drain right-of-way.
Data center siting and county ordinance under moratorium
The six-month moratorium on data centers ends October 8, so the county is racing to finish the ordinance. A special Plan Commission meeting on October 7 could extend the moratorium or advance the ordinance — or both.
Water and aquifer protection
Members worried private wells could drain the aquifer with no enforcement leverage, which is why the draft requires exclusive municipal water and sewer ties — and bans evaporative cooling after public testimony. Commenters raised contaminant concentration and fish-kill concerns.
Drainage tile concerns on Sharon Subdivision lot split
A neighbor with a history of basement flooding asked that an old private clay tile be shown on the plat map before the Wittes' lot split gets recorded. Staff pointed to existing recorded conditions barring obstruction of tile drainage; the drainage board issue remains a separate matter.
Ora Bohler reconstruction assessments and federal wetland relief
The window for judicial review of the Ora Bohler drain project has passed, so the Surveyor's Office is pursuing railroad and state permits before putting the project out to bid.
Chapman Trails Phase III drainage concerns
Neighbors near Basket Factory Road worry that rerouting the Almira Teutsch Lateral 2 drain will send more water toward properties with a broken abandoned tile and a shallow, flood-prone ditch. The developer will fund the drain reconstruction, but maintenance questions will be answered at the secondary plat stage.
Courthouse security improvements
Judges and Sheriff Thomas raised serious concerns about courtroom security, requesting three new deputy positions to ensure deputies are present in courtrooms. The council reached a consensus to allow the sheriff to explore interim funding and hiring.
Kaleo Farms agritourism pond variance
A new agritourism business off CR 71 needed its pond closer than the usual 75 feet to a regulated drain — the board said yes at 54 feet, after the landowner agreed to relocate the nearby tile at his own expense.
Vulcraft industrial expansion drainage
Vulcraft is building a 125,000-square-foot facility on an 85-acre site near the St. Joe River. The plan reshapes the existing detention pond, adds 48-inch pipes under a new road, and matches existing outflows — plus a spill-containment valve to protect the river.
Accessory dwelling units and minimum house size
An Auburn family can build an in-law apartment in a barn so an 87-year-old mother can live on-site with family care instead of entering a nursing home — which the family noted costs about $13,500 a month. The approval expires in five years and requires removal of the quarters when no longer needed.
Pool setback variance on County Road 3
A Garrett landowner needed to deviate from the 10-foot accessory-structure setback to fit a pool between his house and barn. Because he owns all the adjoining property, the variance has no impact on neighbors — it's purely about working with an odd 2019 property-line split on his own land.
Impact fees for large developments
The county has no impact fees today. Staff suggested the county council and commissioners study them as a way to raise revenue from large commercial or industrial developments, like the data centers in the pipeline.
Shooting range and sporting goods zoning compliance
State law stops the county from denying shooting range expansions, and requires retail sporting goods stores and indoor shooting ranges to be permitted uses in commercial, industrial, and agricultural districts. The county has to add these uses to stay compliant.
Data center ordinance timeline
Before the county writes its data center rules (currently under a moratorium), Purdue's Dr. Roberto Gallardo will field questions at a 5:30 p.m. session on July 15 — recommended by Commissioner Jim Miller to get the public and commission on the same factual page.
State-mandated housing rules review
Starting July 1, 2026, new state law forces counties to compile housing statistics, holds fees to 'reasonably necessary' levels with increases only every five years, and requires a public hearing on local development rules by January 2027. Staff worries it strips local control and leaves the county's fees below actual costs.
Innkeeper's tax increase to 8%
The council moved to raise the hotel/motel tax from 5% to the state maximum of 8%, mostly paid by visitors. Neighboring counties have already gone to 8%. Funds must be spent on tourism promotion; the ordinance vote comes July 15.
Butler contract pay under salary ordinance
A wage ordinance amendment would pay Chris Krafft up to $22,000 extra and Butler support staff stipends for work done under the county's contract with the City of Butler. Amy Demske and Amy Prosser questioned the structure — arguing for more staff or overtime instead — and the council held the ordinance until September for answers from the commissioners.
DeKalb County Veterans Memorial completion
The limestone memorial outside Auburn needs granite panels to engrave veterans' names, at about $62,100 for this final phase. The council agreed by consensus to contribute $13,499 from the council budget, joining contributions from Waterloo, Butler, Garrett, Auburn and the commissioners.
Commercial wheel tax increase
The council voted 4-3 to raise the commercial vehicle wheel tax from $5 to $25 while keeping passenger vehicles at $7.50, matching Auburn's rate. Because Auburn and Garrett now collect their own wheel taxes, county collections have been tiny — about $1,700 by mid-year — and state law prevents stacking.
Lot area variance for single-family homesite on Cedar Lane
County rules require 2 acres for a new lot, but an older 1987 subdivision has half-acre lots. The variance lets a new home and septic system be built by merging two existing lots, without adding homes. The health department found the soils average for septic.
Drain maintenance and bank stabilization
County crews are busy with bank stabilization projects, slowing routine drain maintenance. Work should pick back up as wheat fields are harvested and crops come off.
DQ Chill & Grill in Butler
A new Dairy Queen in Butler got its revised drainage plan approved. The site adds a second drive lane and cross access to a future neighboring development while staying within the stormwater pond's approved capacity. It touches three county regulated drains.
Rural drainage and flooding impacts of new subdivisions
Two big livestock barns, a three-lot replat, and four minor subdivisions all cleared drainage review — meaning new construction and rural homesites can move forward across Auburn, Spencerville, Saint Joe and surrounding townships.
Lakewood Park School Athletic Expansion
The school's multi-phase athletic complex begins with tennis courts; future phases will bring ball diamonds and require storm retention and rerouting of county-regulated drains.
Deputy pay competitiveness
Sheriff's deputies start at $64,000 — about $3,000 below the northeast Indiana average and below Auburn PD's $69,000. Sheriff Biddle asked for a modest raise to stop falling behind, noting a new deputy takes a year to train and losing one sets the county back badly.
DeKalb Humane Society funding dispute
The commissioners stopped the county's $50,000 annual payment to the DeKalb Humane Society after the organization rejected five draft contracts. The money now goes to other shelters like Sher Roberts and Fort Wayne Humane, and the commissioners say no funds will flow without a contract and accountability.