Ora Bohler reconstruction assessments and federal wetland relief

Summary

A major reconstruction of the Ora Bohler drain and its laterals is estimated at $776,367, with a new $10/acre base maintenance rate (about $7,548/year versus ~$4,500 now) not charged until five years after construction. A public hearing is set for July 9, 2026.

At a glance

Total mentions
4
Last 30 days
0

Discussed at 1 meeting in the last 60 days; most recently Oct 1, 2026.

Impact analysis

💰Financial impact

$776,367 project cost; affected landowners would see the maintenance rate rise from about $4,500 to $7,548 a year watershed-wide ($10/acre base).

✅Who benefits

Landowners in the watershed get a functioning, maintained drain and better drainage after fall construction.

⚠️Who could be affected

Watershed landowners will pay the higher $10/acre maintenance assessment starting five years after the work wraps up.

Mentions & discussions (4)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for DeKalb County

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.