Civic Issues
Topics getting the most attention in Avon public meetings, ranked by how frequently they are discussed.
8 issues in water utilities
Stormwater ordinance amendment (Ordinance 2026-17)
The stormwater board changed how it operates, including lien procedures, so the town code needs to match. An amendment was introduced to keep everything in compliance — a vote comes at a future meeting.
Blue Peninsula sanitary easement at Dan Jones and CR 100 N
The Wawa developer needed to run a private sewer line under a sliver of town-owned land at Dan Jones and CR 100 N. The town granted a permanent easement for $1,977.12; the underground line won't block future roundabout improvements and will be recorded on the town's GIS.
Stormwater Delinquency and Lien Process Overhaul
Ordinance 2026-13 gives the stormwater board flexibility on delinquency notices and lien filings, saving the cost of certified mailings on hundreds of accounts while still protecting the town's legal rights.
Easton Grey Water Line Easement
The town granted an easement along County Road 600 East so the Easton Grey development can loop its water line, ensuring reliable water pressure and supply on both sides of the project.
Foundation Park sanitary sewer connection
West Central Conservancy District is forcing the town to connect Foundation Park to sewer by August 19 or face $1,000-a-day fines. The tap fees plus the Daystar contract total about $138,433 that wasn't budgeted, coming out of parks programming funds.
Foundation Park sanitary sewer
West Central Conservancy District is forcing the town to abandon the ballpark's 44-year-old septic system and connect to sewer, and has started fining the town $250 a day past its 90-day deadline. The fix costs about $46,500 and wasn't budgeted, so something else in the parks budget gets cut.
Fiber internet expansion in Avon
Joink LLC is expanding underground fiber internet service in Avon, and this tiny equipment building is the hub that boosts service across its build area. Construction is expected around April 2026.
Easton Grey Waterline Easement Reroute
Contractors installing the Easton Grey waterline couldn't tunnel under the creek as planned, so the easement is being shifted to a shallower, more direct crossing — with the old easement released back to the town. The new location actually works better for future development.