Foundation Park sanitary sewer
Summary
West Central Conservancy District is forcing the town to abandon the ballpark's 44-year-old septic system and connect to sewer, and has started fining the town $250 a day past its 90-day deadline. The fix costs about $46,500 and wasn't budgeted, so something else in the parks budget gets cut.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Jul 9, 2026.
Impact analysis
About $46,500 plus $250 per day in fines that were accruing while the town deliberated.
Families and teams using the ballpark fields get reliable restrooms, and the town avoids escalating fines.
Parks projects the town had planned to fund this year may be cut to cover the unbudgeted expense.
Mentions & discussions (2)
Town Council Work Session (Work) - Jul 9, 2026
The sewer project at Foundation Park is expected to cost in the low six figures. A health department waiver to fill the old tank instead of removing it saved money and protects the building above.
Town Council Work Session (Work) - May 14, 2026
West Central Conservancy District is forcing the town to abandon the ballpark's 44-year-old septic system and connect to sewer, and has started fining the town $250 a day past its 90-day deadline. The fix costs about $46,500 and wasn't budgeted, so something else in the parks budget gets cut.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Avon
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.