Culvert replacements funded ahead of schedule
The engineer plans to buy two large concrete box culverts now — about $52,000 and $63,000 — using this year's budget, so next year's money stretches further. Structures last 50-plus years and no formal vote was needed.
Bridge 27 replacement on Piqua Road
The county signed off on an INDOT grant application to replace the Piqua Road bridge over the Gerke Ditch. Construction bids go out in July 2026, with work hopefully wrapped before the end of 2027.
Chip seal program performance
The highway department has chip-sealed 40 miles of county road so far and is aiming for 110 miles this year. Extreme heat slowed work last week, but crews are back on pace.
Stormwater pipe project struggles on 600 East
The Colbert 239 pipe replacement between 400S and 500S hit soft muck soils, with trench collapses and road cracking pushing the job well past schedule. Contingency funds are absorbing the extra cost.
Bridge repairs south of 218
Engineer Nate Rumschlag flagged four bridges — 162, 149, 166 and 143 — damaged by heavy farm traffic, with deck damage that will grow into bigger repairs if not fixed soon.
Vacation of Bridge #163 and W 1100 S
The county gave up a road and bridge it no longer wants to maintain, transferring them to adjoining owners including Red Gold. Remaining county parcels may be quit-claimed to Red Gold in exchange for a drainage-access easement.
Courthouse two-hour parking enforcement
Tired of cars camping in county lots? Ordinance 2026-4 would ban long-term storage parking, inoperable vehicles, and non-emergency repairs on county property. Public hearing and adoption are still ahead.
Bridge 163 and CR 1100 South vacation
A little-used road and bridge would cost roughly $2.5 million to fix, with a county share near $500,000. The county will instead vacate it, transferring ownership to adjacent landowners and ending county liability.
Newly discovered park bridge needing inspection
A little bridge in a Decatur park that carries car traffic was never on the county's bridge inventory. It's now Bridge 45 and will be inspected, load rated, and possibly posted with signs — which may surprise park visitors.
Bridge 86 repair cost overrun
A planned $3,000–$4,000 joint repair on Bridge 86 turned into a roughly $15,000 patch after crews found worse delamination than expected — but officials say it beat a $300,000 superstructure replacement.
Highway department projects and equipment
Paving on CR 000 and 700 is wrapping up, Bridge 31 and Bridge 96 work continues, and unused equipment heads to online auction while a $28,000 mower bid was accepted.
2026 HMA paving project bids
The board locked in this year's road work: about three miles of paving by Brooks Construction at a notably low bid, plus new trucks and a tandem axle equipment build. Crews meanwhile keep battling snow drifts and a few equipment breakdowns.
Road and bridge vacation east of Geneva
The county is moving to vacate CR1100S and Bridge 163 east of Geneva — partly tied to Red Gold's property. The legal description is in hand and a public hearing will be scheduled.
Guardrail hit-and-run on CR 200N
A driver slid off County Road 200N east of Salem Road, rode up the guardrail, and fled the scene — leaving the county with no one to bill for repairs. The engineer is also phasing out this guardrail design in future projects because of how it performs in crashes.