Bridge 27 replacement on Piqua Road
Summary
The county signed off on an INDOT grant application to replace the Piqua Road bridge over the Gerke Ditch. Construction bids go out in July 2026, with work hopefully wrapped before the end of 2027.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 6, 2026.
Impact analysis
Federal-aid funded; detour plans are the main local impact.
Drivers who use Piqua Road northwest of the US-27 intersection get a safer bridge.
Local traffic faces a detour during construction.
Mentions & discussions (4)
Board of Commissioners - Oct 6, 2026
Bridge 27 over Pickle Road gets a preconstruction meeting this week with a January 2027 start; detour routes will be publicized, and a utility error by BFNS is being corrected at their expense.
Board of Commissioners - Jul 14, 2026
Bids came in for replacing Bridge 27 over the Gorkey Ditch, with Milestone Contractors the low bidder at $1.38 million — about $25,000 over the engineer's estimate. Work could start late this year or next spring.
Board of Commissioners - Jun 30, 2026
A full replacement of Bridge 27 between CR 000 and 850N goes to bid July 8 and could start this year, with about 180 days of road closure and a fall or spring detour.
Board of Commissioners - Mar 3, 2026
The county signed off on an INDOT grant application to replace the Piqua Road bridge over the Gerke Ditch. Construction bids go out in July 2026, with work hopefully wrapped before the end of 2027.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Adams County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.