Stormwater pipe project struggles on 600 East
Summary
The Colbert 239 pipe replacement between 400S and 500S hit soft muck soils, with trench collapses and road cracking pushing the job well past schedule. Contingency funds are absorbing the extra cost.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jul 14, 2026.
Impact analysis
Contingency funds are being used; the project won't stay on its original estimate.
Residents who rely on 600 East once the drainage fix is complete.