Civic Issues
Topics getting the most attention in Valparaiso public meetings, ranked by how frequently they are discussed.
3 issues in water utilities
Utilities infrastructure projects
Big sewer separation and water main work coming to Franklin Street, plus a lead service line replacement project backed by $2.5 million in grant and $2.5 million in 0% loan money.
Water system replacement wells
The city's utility is planning five new wells on RDC park property, with three wells and a transmission main along Burlington Beach Road in 2026-27, to stay ahead of aging wells and glacial soil challenges. Test wells at the Country Club and Flint Lake failed despite past productivity.
Franklin Street Improvements (2027)
Water main, storm sewer, and road work on Franklin Street will be combined into one project totaling about $1.9 million. Bids open November 10.