Water system replacement wells
Summary
The city's utility is planning five new wells on RDC park property, with three wells and a transmission main along Burlington Beach Road in 2026-27, to stay ahead of aging wells and glacial soil challenges. Test wells at the Country Club and Flint Lake failed despite past productivity.
At a glance
- Total mentions
- 2
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 26, 2026.
Impact analysis
VCU has spent $33 million on water infrastructure over the past decade, with well bores costing $20,000-$30,000 each.
All water customers get a more reliable supply as the city stays ahead of aging wells.
Property near the new well sites may see land disturbance, though coordination with park projects aims to minimize it.
Mentions & discussions (2)
City Council - Oct 26, 2026
Councilman Moore reported that the Utilities Board selected Lock Miller to lead lead-service-line replacement under a State Revolving Fund project with a $2.5 million grant and a $2.5 million 0% loan, plus a major Franklin Street sewer and water main project.
Redevelopment Commission - Apr 9, 2026
The city's utility is planning five new wells on RDC park property, with three wells and a transmission main along Burlington Beach Road in 2026-27, to stay ahead of aging wells and glacial soil challenges. Test wells at the Country Club and Flint Lake failed despite past productivity.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Valparaiso
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.