Water system replacement wells
The city's utility is planning five new wells on RDC park property, with three wells and a transmission main along Burlington Beach Road in 2026-27, to stay ahead of aging wells and glacial soil challenges. Test wells at the Country Club and Flint Lake failed despite past productivity.
NIPSCO labor lockout affecting Valparaiso residents
The council unanimously backed the steelworkers' call for an investigation into NIPSCO's staffing cuts. Local linemen are stretched thin — 8 linemen cover the whole Valparaiso territory — and the August 11 storm response exposed the gaps. Portage and Michigan City passed similar measures.
Eastside Water Well
VCU began building three Eastside wells in September after replacement testing failed at Flint Lake and Country Club. One of the five original sites was a dud, and the new southeastern site near mapped wetlands tested well and won IDEM approval — but the middle well's 40-foot easement and 100-foot sanitary setback sit in the middle of planned mixed-use development land.
Free V-Line service during storm recovery
With power still out across parts of the city, V-Line buses will stay free until further notice. City Administrator Steve Poulos will decide when fares come back.
Waterworks Revenue Bonds for new wells and transmission main
The city is borrowing up to $10 million to drill three new wells and build an 11,200-foot transmission main before aging wells at Country Club and Flint Lake fail. No water rate increase is needed — revenues are outperforming projections.
Lead service line replacement funding
The city applied for a $7.7 million state revolving fund grant to replace all 499 known lead service lines, including home restoration. Even in an all-loan scenario, officials say rates won't need to rise.
Stormwater Improvements on Lois Dr, Central Ave, Evergreen Dr
The city opened bids for long-awaited stormwater drainage improvements in these neighborhoods, but all four bids came in above the $871,000 estimate — the lowest at about $916,000. A recommendation on awarding the contract comes at the next meeting.
ValpoNet Repair Proposal
Following multiple fiber cuts by a contractor in September along Division Road, the city is working on permanent repairs and coordinating with Valpo City Utilities and Indiana 811 to prevent future utility strikes.
VLACD Conservancy District litigation and VCU intervention
A freeholder petition filed in January in Porter County Circuit Court seeks restructuring of the Valparaiso Lakes and Area Conservancy District, potentially opening the door to city utilities taking over service. The city says it didn't file the petition and intervened only to protect ratepayers; a full evaluation would cost well into six figures.