23 issues in roads

MediumRoads

Jessee-Pifer neighborhood sidewalks and 2026 sidewalk program

Two big sidewalk packages went out for bid: about 18,000 square feet of replacements (estimate $400,000) and new pathways along Froberg Road and 500 North (estimate $617,000). Concrete bids came in competitive; awards will be recommended at the next meeting.

5 mentions (1 this month)Last discussed Nov 13, 2026
MediumRoads

Multi-use trail expansion (TOD to downtown; Silhavy at CN tracks)

A new 1,400-foot trail will connect downtown to the Transit Oriented District, funded mostly by federal highway money ($4 million total). Construction could start next spring after tree clearing in the winter.

5 mentions (1 this month)Last discussed Nov 13, 2026
HighRoads

2027-1 Community Crossings and paving

Two bids came in for the state-funded Community Crossings road work, both above the $2.65 million estimate. The board holds off on awarding until engineers review them and return a recommendation.

11 mentions (1 this month)Last discussed Nov 13, 2026
LowRoads

Mound Street closure

A Mound Street closure involving Egolf Coates Excavating was scheduled for action. Closures can affect local traffic access during construction.

1 mention (1 this month)Last discussed Nov 13, 2026
LowRoads

Snow removal contract for LHG

A snow removal proposal for LHG was on the agenda, covering winter maintenance costs at that site.

1 mention (1 this month)Last discussed Nov 12, 2026
MediumRoads

Stormwater, water main, and street improvement projects

Big sewer separation and water main work coming to Franklin Street, plus a lead service line replacement project backed by $2.5 million in grant and $2.5 million in 0% loan money.

2 mentions (1 this month)Last discussed Oct 26, 2026
HighRoads

Lincolnway–Campbell Roundabout Right-of-Way

The city is using condemnation to finish acquiring land for a roundabout at one of its crash-prone intersections — 31 crashes, six with injuries, in five years. Construction is planned for 2028.

2 mentions (1 this month)Last discussed Oct 23, 2026
LowRoads

Joliet Road Closure

NIPSCO will close Joliet Road at Skyline Drive for about two days starting November 2 to repair a gas main leak; detours are planned and city facilities stay accessible.

2 mentions (1 this month)Last discussed Oct 23, 2026
MediumRoads

2027 Asphalt Rejuvenation Program

Twelve recently paved local streets will get a rejuvenator treatment meant to stretch pavement life by 5 to 7 years, at a cost of $106,311.

1 mention (1 this month)Last discussed Oct 23, 2026
HighRoads

G&L Superload Hauls Through City Streets

Five transformer hauls weighing about 770,000 pounds gross will roll through town starting November 14, every other day through the 22nd. The Board conditioned approval on extra engineering review and bonding to protect roads and water/sewer lines.

1 mention (1 this month)Last discussed Oct 23, 2026
MediumRoads

Lincolnway street closure

Lincolnway between Campbell and Weston will fully close for about two weeks starting around September 28 for storm sewer separation work. Commuters and downtown businesses should plan for detours.

3 mentionsLast discussed Oct 9, 2026
MediumRoads

Division Road improvements for Pratt truck traffic

Up to $2 million in early TIF revenue will front-load Division Road reconstruction for truck traffic, with an interlocal agreement with the county still to be negotiated on scope, timing, and cost sharing.

1 mentionLast discussed Oct 8, 2026
HighRoads

2026-1 Community Crossings road improvements

The city is chasing an $896,000 state grant toward roughly $2 million in road work next year, selected by PACER ratings. The rest comes from local paving funds.

4 mentionsLast discussed Sep 11, 2026
MediumRoads

Institute St road improvements change order

City Utilities seeks bids to replace about 830 feet of aging 6-inch water main serving the Kirchoff Park and Parkview Elementary area, which has had seven main breaks — three in the last five years.

2 mentionsLast discussed Sep 11, 2026
MediumRoads

Madison Street closure

Madison Street near Family Express closes for up to two weeks starting September 8 while underground fuel tanks are replaced. Homeowners keep access from the north, and a detour is in place.

1 mentionLast discussed Aug 28, 2026
MediumRoads

2026 Crack Seal Program

Crack sealing got rescoped down to $141,750 after a high sole bid, and three alley paving quotes were opened — Boyd Asphalt came in almost exactly at estimate. The alley award decision comes next meeting.

3 mentionsLast discussed Aug 14, 2026
HighRoads

Montdale Park Road Reconstruction

Only one bid came in for the $2.3 million road rebuild — $2.47 million from Milestone. Staff will review before recommending whether to award.

3 mentionsLast discussed Aug 14, 2026
MediumRoads

Montdale Drive reconstruction

The long-planned rebuild of Montdale Park Drive moved forward with a $2.47 million contract to Milestone Contractors — slightly over estimate on a single bid received during peak paving season.

1 mentionLast discussed Aug 13, 2026
HighRoads

Citywide Safety Action Plan

A federally funded plan ranks the 12 most dangerous road locations and will now shape street, sidewalk and grant priorities — with Calumet Avenue a top corridor for a future master plan.

1 mentionLast discussed Aug 10, 2026
MediumRoads

Pepper Creek private street dedication

The city formally accepted roughly 3,700 linear feet of private streets at the Courtyards of Pepper Creek into its public road system. The HOA repaves first and the city covers 25% of that cost; landscaping and storm infrastructure stay with the HOA.

1 mentionLast discussed Jul 24, 2026
HighRoads

2026 Local Streets Paving Program

The city opened bids for this year's neighborhood paving work. The low bid from Milestone Contractors comes in under the engineer's estimate, and a recommendation is expected at the next meeting.

5 mentionsLast discussed Jun 26, 2026
MediumRoads

Froberg Road closures for sidewalk project

Sidewalk work starting April 20 will close stretches of Froberg Road in three phases on weekdays from 7 a.m. to 5 p.m., with one week's advance notice. The project will connect Regatta, Pepper Creek, Irongate, and future Midwood neighborhoods.

3 mentionsLast discussed Jun 26, 2026
MediumRoads

US 30 & Silhavy Roundabout Cost Increase

Old hotel foundations found during construction added $76,255.76 and four days to the roundabout project, paid from State Road 130 relinquishment funds.

1 mentionLast discussed Jun 12, 2026