Medium PriorityRoadsopen

Montdale Drive reconstruction

Summary

The long-planned rebuild of Montdale Park Drive moved forward with a $2.47 million contract to Milestone Contractors — slightly over estimate on a single bid received during peak paving season.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Aug 13, 2026.

Impact analysis

💰Financial impact

$2,473,195.59, funded from the commission's existing budget.

✅Who benefits

Motorists and businesses in the Montdale Park area get a rebuilt road.