13 issues in roads with medium priority
Multi-use trail expansion (TOD to downtown; Silhavy at CN tracks)
A new 1,400-foot trail will connect downtown to the Transit Oriented District, funded mostly by federal highway money ($4 million total). Construction could start next spring after tree clearing in the winter.
Jessee-Pifer neighborhood sidewalks and 2026 sidewalk program
Two big sidewalk packages went out for bid: about 18,000 square feet of replacements (estimate $400,000) and new pathways along Froberg Road and 500 North (estimate $617,000). Concrete bids came in competitive; awards will be recommended at the next meeting.
Stormwater, water main, and street improvement projects
Big sewer separation and water main work coming to Franklin Street, plus a lead service line replacement project backed by $2.5 million in grant and $2.5 million in 0% loan money.
2027 Asphalt Rejuvenation Program
Twelve recently paved local streets will get a rejuvenator treatment meant to stretch pavement life by 5 to 7 years, at a cost of $106,311.
Lincolnway street closure
Lincolnway between Campbell and Weston will fully close for about two weeks starting around September 28 for storm sewer separation work. Commuters and downtown businesses should plan for detours.
Division Road improvements for Pratt truck traffic
Up to $2 million in early TIF revenue will front-load Division Road reconstruction for truck traffic, with an interlocal agreement with the county still to be negotiated on scope, timing, and cost sharing.
Institute St road improvements change order
City Utilities seeks bids to replace about 830 feet of aging 6-inch water main serving the Kirchoff Park and Parkview Elementary area, which has had seven main breaks — three in the last five years.
Madison Street closure
Madison Street near Family Express closes for up to two weeks starting September 8 while underground fuel tanks are replaced. Homeowners keep access from the north, and a detour is in place.
2026 Crack Seal Program
Crack sealing got rescoped down to $141,750 after a high sole bid, and three alley paving quotes were opened — Boyd Asphalt came in almost exactly at estimate. The alley award decision comes next meeting.
Montdale Drive reconstruction
The long-planned rebuild of Montdale Park Drive moved forward with a $2.47 million contract to Milestone Contractors — slightly over estimate on a single bid received during peak paving season.
Pepper Creek private street dedication
The city formally accepted roughly 3,700 linear feet of private streets at the Courtyards of Pepper Creek into its public road system. The HOA repaves first and the city covers 25% of that cost; landscaping and storm infrastructure stay with the HOA.
Froberg Road closures for sidewalk project
Sidewalk work starting April 20 will close stretches of Froberg Road in three phases on weekdays from 7 a.m. to 5 p.m., with one week's advance notice. The project will connect Regatta, Pepper Creek, Irongate, and future Midwood neighborhoods.
US 30 & Silhavy Roundabout Cost Increase
Old hotel foundations found during construction added $76,255.76 and four days to the roundabout project, paid from State Road 130 relinquishment funds.