8 issues in roads with medium priority
Community Crossings grant denial
The county's repaving application for the Angola-to-Blake corridor was denied — no data flaws, just too many applicants. Commissioner Laughlin vented that the state funded other projects without traffic data while the county got 1.5 million a year before the program was paused.
C.R. 27 resurfacing via Community Crossings grant
Storm delays pushed the 2026 road program back a week, but chip sealing is underway. The county will apply for Community Crossing grant funds to pave Old 27 from Angola to Pleasant Lake in 2027.
Pleasant Lake Speed Limit and No-Parking Ordinance
Two new traffic ordinances got first-reading approval: a 35 mph limit on CR 475 S/1000 W and 20 mph/no-parking rules on Pleasant Lake streets residents requested. Two more readings are needed before they take effect.
100 N / 200 W Roundabout Project
NIPSCO gas relocation at the roundabout finishes mid-June, then REMC and Frontier relocate utilities; the road won't close for actual construction until Spring 2027, when Brooks Construction gets up to 120 days.
Highway projects and 2027 budget
Progress on the roundabout, Poka-Bache trail right-of-way, chip seal and striping programs, plus a 2027 draft budget with no raises and no new full-time positions. Concerns remain about projected Fund 1176 revenue.
Unmaintained County Road 500 N right-of-way
A property owner asked about a crossing on a road the county hasn't maintained since the 1970s-80s and collects no tax revenue on. The county won't spend money on it; the related deed/assignment was tabled and may go to the Drainage Board because landlocked parcels depend on it.
Urban SDK Traffic Data — 2027 Budget Item
The Highway Engineer wants a $40,000-a-year service that provides up-to-date traffic counts and speed data on every county road, including gravel roads he can't count manually. It could support future grant applications and big developments like the potential casino or Crooked Lake projects, but funding for 2026 isn't identified yet.
Airport Funding and Snow Equipment
The airport board delivered a $42,500 fuel-sale check and is getting FAA-grant-funded snow removal equipment plus hangar insulation and heaters so the new machine can be stored properly. They also flagged a new state law that could return airport fuel money to the airport, saving the county about $40,000.