100 N / 200 W Roundabout Project
Summary
NIPSCO gas relocation at the roundabout finishes mid-June, then REMC and Frontier relocate utilities; the road won't close for actual construction until Spring 2027, when Brooks Construction gets up to 120 days.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jun 2, 2026.
Impact analysis
Motorists will eventually get a safer intersection after construction closures in 2027.