Medium PriorityRoadsopen

100 N / 200 W Roundabout Project

Summary

NIPSCO gas relocation at the roundabout finishes mid-June, then REMC and Frontier relocate utilities; the road won't close for actual construction until Spring 2027, when Brooks Construction gets up to 120 days.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jun 2, 2026.