Top issues during term (16)(Water Utilities)

high↑Jun 2026[27]

Barr Tile storm drain reconstruction in Topeka

Roughly half a million dollars in construction plus about $60,000 in engineering oversight.

high↑Oct 2026[15]

Sarah Davis #5 rock intrusion at flea market

Another jetting could cost $5,000–$6,000, and a permanent fix will cost more; the board is weighing whether one entity should pay instead of the whole watershed.

medium↑Oct 2026[15]

Francis #9 crossing at SR 3 and INDOT cost-sharing

The county could be stuck with up to $123,000 of a $160,000 project if INDOT's position holds.

high↑Nov 2026[13]

Fish/Royer Lake channel dredging

A small new assessment would hit watershed property owners after a February public hearing, since only $14,260 is on hand against an $80,000-$100,000 project.

medium↓Oct 2026[6]

Sewer Tap-In Fee Costs and Housing Affordability

Connecting a new home to the regional sewer district can cost roughly $27,000 before construction, a major hurdle for affordable housing.

low↓Oct 2026[5]

Cochran ditch cleaning at Stroh on hold

low↓Sep 2026[5]

Drainage discharge onto neighboring property

Potential future drainage complaints or washout repairs could fall on the neighboring property owner.

high↓Oct 2026[5]

Wuthrich #215 funding shortfall

Cost unknown until a hearing sets an assessment on landowners in the watershed.

high↓Sep 2026[5]

Yeager #134 drain repairs and INDOT reimbursement

County pays $100,000 up front, hoping to recoup about $45,000–$47,000 from INDOT.

medium↓Sep 2026[5]

Lakeside Park storm drain failure

Up to $6,000 from the county's drain cost-share fund.

high↓Aug 2026[2]

Mirror Lake pond lowering

No dollar figure was given for the control-structure modification; work should be done within a few weeks.

medium↓Jul 2026[2]

Stormwater drainage at northern Indiana lakes

Builders will bear the cost of drainage tile, grading, and stormwater plans as permit conditions.

medium↓Jun 2026[2]

Commercial well and septic separation rules for farm operations

Drilling a new commercial well could cost the owner thousands of dollars if the existing house well can't be used.

medium↓Apr 2026[1]

Drainage right-of-way encroachment enforcement

Delays could cost the landowners time on their projects but no county dollars are at stake yet.

high↓Mar 2026[1]

Adams Lake inlet maintenance funding

Cleaning will cost $22,500–$51,000; restarting the assessment fund means landowners in the watershed pay in again, likely in the year after the hearing.

medium↓Mar 2026[1]

Buck Creek reimbursement to Roy Miller

The county's drainage fund is out $8,485.88, but the board considers it money already owed.

Decisions during term (0)

Recorded while Campos was in office — not necessarily decisions they moved, spoke to, or voted on.