The Barr Tile acts more like Topeka's storm sewer than a farm drain, and a collapsed section still needs replacing — estimated around $500,000. The town is fixing road crossings, and the board must pick an engineering firm to oversee the rest, with only one proposal so far.
At a glance
- Total mentions
- 6
- Last 30 days
- 2
Discussed at 2 meetings in the last 60 days; most recently Nov 4, 2026.
Impact analysis
Roughly half a million dollars in construction plus about $60,000 in engineering oversight.
Topeka residents whose streets and ponds flood when the tile fails.
The Surveyor says the lack of communication put him in a difficult professional position.
Mentions & discussions (5)
Drainage Board - Nov 4, 2026
The 1980s-era storm drain serving most of Topeka has corroding metal pipe, shallow cover and utilities bored through it. The county is paying Engineering Resources about $70,100 to design and oversee a rebuild of 3,000 feet, with construction above $500,000 planned for fall 2027.
Drainage Board - Oct 7, 2026
A major overhaul of the Barr Tile through Topeka is moving forward with ERI as engineer after no other firms would take the job. The drain's role has changed from farm drain to urban stormwater with Forest River and medical offices nearby.
Drainage Board - Sep 9, 2026
The Barr Tile acts more like Topeka's storm sewer than a farm drain, and a collapsed section still needs replacing — estimated around $500,000. The town is fixing road crossings, and the board must pick an engineering firm to oversee the rest, with only one proposal so far.
Drainage Board - Jul 8, 2026
Surveyor Holsinger publicly challenged the commissioners over how the board's recent reformation was handled without notice to him, calling the process hasty and unprofessional. The commissioners said they replaced the board, not the surveyor, and asked him to work better with county government.
Drainage Board - Jun 3, 2026
The board received a bid from Engineering Resources, Inc. for work needed on the Barr #77 tile and will review it — same drain the new driveway was approved over.
Related development
Town of Topeka — deteriorating pipe replacement — Barr Tile #77
Better flow from the new pipe may ease the reverse-flow problems residents have seen filling the pond during heavy rains.
NIPSCO Barr Tile #77 utility replacement
Utility service improvements proceed without crossing or altering the tile.
Zeigler/Yoder driveway – Barr #77 tile
A new farm driveway over a county tile — approved as presented.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for LaGrange County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.