County Road 1000 North extension federal grant application
The path was dropped from the road-widening scope to fit federal funding, leaving the Austin Winds area without safe walkways despite heavy traffic growth. The county publicly committed to building an acceptable path in a later phase.
County Road 200 North gap closure and CR 600 North pedestrian safety
A $750,000 study recommends a new traffic signal at Eagle Crossing Boulevard — where a pedestrian was hit in 2025 — plus crosswalk, ramp, and signal upgrades at five other intersections. No money is budgeted yet; the engineer will look for grants and bring funding options back.
Ronald Reagan Parkway completion to Boone County
Three road-spending items moved forward: $56,206 for INDOT asphalt testing on the parkway extension, $36,000 more for CR 1000 N. design, and $368,707 to rejuvenate 26 miles of county asphalt.
Municipal Wheel Taxes and Community Crossing Funding
The county missed an earlier Community Crossings award, but Senate Bill 179 is restructuring the program and could bring funding this fiscal year. A notice to bidders was pre-approved so the county can move fast if funds arrive.
Roundabouts at State Road 39 and I-70
The county is taking the lead on roundabouts and access improvements at SR 39 and I-70 for the Sunbeam warehouse development, including a truck-stop access realignment. Engineers showed the drainage board that stormwater impacts are minimal and no detention is needed.
CSX Bridge 290 Cost Increase
The county must pay CSX nearly $580,613 more for engineering, inspection and flagging on the Dan Jones Road bridge project — almost double the original estimate, partly due to a 40 percent jump in flagger rates.
Bridge No. 49 Rehabilitation on CR 350 N
The county opened five bids to replace Bridge No. 49 on CR 350 North over White Lick Creek, with the low bid at $737,564. The award recommendation is expected in two weeks.
CR 700 N Closure and SR 267 Detour Traffic
With CR 700 N closed, traffic is being monitored at the CR 800 N and SR 267 intersection. Two recent SR 267 accidents were not related to the detour, but residents are watching speeds and safety signage.