Roundabouts at State Road 39 and I-70
Summary
The county is taking the lead on roundabouts and access improvements at SR 39 and I-70 for the Sunbeam warehouse development, including a truck-stop access realignment. Engineers showed the drainage board that stormwater impacts are minimal and no detention is needed.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Last discussed Aug 4, 2026.
Impact analysis
County share previously estimated near $8 million total, reduced by developer and state contributions.
Warehouse traffic on the county's busiest corridor gets safer, better-flowing access.
Slightly more paved area sends marginally more stormwater toward Morgan County.
Mentions & discussions (4)
Council Budget Hearings — August 4, 2026
County committed $6 million toward three roundabouts near I-70 and $3.5 million as local share of the 1000 North reconstruction, funded largely by relinquishment dollars and wheel tax.
Hendricks Co. Joint Council / Commissioner's — June 16, 2026
Nearly every official put these roundabouts at or near the top of the list, citing truck traffic and safety — but the funding isn't nailed down yet, as developer contributions are still pending.
Hendricks Co. Commissioner's — April 28, 2026
The county is taking the lead on roundabouts and access improvements at SR 39 and I-70 for the Sunbeam warehouse development, including a truck-stop access realignment. Engineers showed the drainage board that stormwater impacts are minimal and no detention is needed.
Hendricks Co. Joint Council / Commissioner's — April 28, 2026
Three roundabouts at SR 39 and I-70 are moving ahead, with the two north of I-70 built first and developer cost-sharing being negotiated.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Hendricks County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.