Phase One Contract D water project change orders

Three change orders cover pothole patching on Madison Avenue, replacing an old stormwater inlet at Sixth and Madison, and an eight-day extension after flooding shut down construction.

1 mention (1 this month)Last discussed Nov 10, 2026
MediumWater Utilities

Edgewood Plaza Sewer Improvements

Drainage work near Nichol and Raible hit an uncharted private water line, and the repair will cost the commission $11,610. Nobody could have flagged it beforehand — 811 didn't have it either because it was privately built in the late 1950s.

3 mentions (2 this month)Last discussed Nov 10, 2026
MediumWater Utilities

State revolving fund loan disbursements

Nearly $890,000 in disbursement requests for the water infrastructure improvement project were approved and sent to the Indiana State Revolving Fund for payment.

3 mentions (1 this month)Last discussed Nov 4, 2026
MediumWater Utilities

Dewey Street Dry Weather Pump Station rehabilitation

The board approved a $134,044 progress payment to F.A. Wilhelm for pump station work, part of the city's dry weather lift station rehabilitation program.

2 mentions (1 this month)Last discussed Nov 4, 2026
MediumWater Utilities

Division Three Well and Raw Water Main Project completion

The city is spending about $100,000 (mostly grant/loan funded) to find out how much drinking water capacity remains in its wellfields. This helps plan for future water supply reliability on the south side and at the Lafayette Well Field.