Phase One Contract D water project change orders
Summary
Three change orders cover pothole patching on Madison Avenue, replacing an old stormwater inlet at Sixth and Madison, and an eight-day extension after flooding shut down construction.
At a glance
- Total mentions
- 1
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 10, 2026.
Impact analysis
About $19,500 in added costs, plus a no-cost schedule extension.
Residents who rely on the water infrastructure along Madison Avenue.