Phase One Contract D water project change orders
Three change orders cover pothole patching on Madison Avenue, replacing an old stormwater inlet at Sixth and Madison, and an eight-day extension after flooding shut down construction.
Edgewood Plaza Sewer Improvements
Drainage work near Nichol and Raible hit an uncharted private water line, and the repair will cost the commission $11,610. Nobody could have flagged it beforehand — 811 didn't have it either because it was privately built in the late 1950s.
Dewey Street Dry Weather Pump Station rehabilitation
The board approved a $134,044 progress payment to F.A. Wilhelm for pump station work, part of the city's dry weather lift station rehabilitation program.
State revolving fund loan disbursements
Nearly $890,000 in disbursement requests for the water infrastructure improvement project were approved and sent to the Indiana State Revolving Fund for payment.
Division Three Well and Raw Water Main Project completion
The city is spending about $100,000 (mostly grant/loan funded) to find out how much drinking water capacity remains in its wellfields. This helps plan for future water supply reliability on the south side and at the Lafayette Well Field.
CATS Bus Service Expansion Requests
Anderson's transit system (CATS) sought a contract amendment with its equipment vendor Leswego Corp dba Angelin Equipment. Amendments like this often cover additional equipment purchases or repairs for the city fleet.
Electric rate increase via Q4 tracker
The Light and Power tracker will add $4.90 (4.82%) to customer bills for October through December, driven by purchased power costs. Hot weather in the prior quarter pushed supplier costs up.
Longwood Avenue Storm Replacement Project
Bids came in wildly uneven — from $87,900 to nearly $400,000 against a $96,500 estimate — so the board is holding off on picking a contractor for this drainage work.
Lafayette Treatment Plant Expansion — Change Order #3
A third change order was on the docket for the Lafayette Treatment Plant expansion. It could affect the cost or timeline of expanding the city's water treatment capacity.
White River Interceptor Phase IIA Liquidated Damages
The Board was set to consider assessing liquidated damages on the White River Interceptor Phase IIA sewer project — typically a penalty when a contractor misses deadlines. Costs tied to the project could affect sewer ratepayers.
Water Main Extension Reimbursement Agreement
A reimbursement agreement for a water main extension was on the agenda, which affects water service infrastructure. No outcome was recorded.