2026 Sewer Improvements Project and Plant Upgrades
Summary
Sewer plant improvements — new pumps, headworks and a backup generator among them — will cost about $9.6 million, with $7.03 million borrowed and repaid from sewer revenues, not general taxes. Final vote could come in February.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Aug 17, 2026.
Impact analysis
Rates were already set with this project in mind in 2025 — the bonds are repaid from sewer revenues, not your property taxes.
Sewer customers, who get a more reliable treatment plant.
Opponents argue ratepayers ultimately absorb the costs baked into the utility's rate base.
Mentions & discussions (3)
Zionsville Town Council - Aug 17, 2026
The town is spending $12.6 million to upgrade the front end of the wastewater plant, which dates to 1983 and is failing. Engineers say capacity remains ample (1.2M of 2M gallons/day used) and no service interruptions are expected. Residents near the plant have complained about odors.
Zionsville Town Council - Mar 2, 2026
The council deadlocked 3-3 on whether to approve Citizens Energy taking over HSE's sewer service agreement for the 421/32 area, stalling a deal that includes a $3 million infrastructure contribution and a 25-year claw-back. A no vote means HSE builds with Citizens treating wastewater; a continued divide tees the question up again March 16.
Zionsville Town Council - Jan 5, 2026
Sewer plant improvements — new pumps, headworks and a backup generator among them — will cost about $9.6 million, with $7.03 million borrowed and repaid from sewer revenues, not general taxes. Final vote could come in February.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Zionsville
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.