Wastewater System Development Charge
Summary
New sewer connections will pay $2,500 to $400,000 depending on meter size, replacing the old flat $400 tap fee, with money going to infrastructure. Builders say they understand the need after staff meetings but worry about housing costs; the Indiana Apartment Association opposes it.
At a glance
- Total mentions
- 6
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 2, 2026.
Impact analysis
Developers and new-home buyers will shoulder higher upfront connection costs — a house pays $2,500 versus the old $400.
Existing ratepayers — new growth helps fund the infrastructure expansion instead of rate increases covering it all.
Builders and multifamily developers — the Indiana Apartment Association warns fees of $15,000-$125,000 per project could slow housing construction.
Mentions & discussions (6)
City Council - Nov 2, 2026
The city is borrowing about $85 million to expand the wastewater plant from 10.5 to 15 million gallons per day to handle coming development, including roughly 5,000 new student beds. Bond rates came in around 4.27%, saving about $7.7 million — and no rate increase is needed.
City Council - Sep 8, 2026
Sewer rates rise 2% a year for four years (a rate study justified up to 10%), and new connections now pay a system development charge from $2,500 to $400,000 by meter size — shifting growth costs onto new users.
Board of Public Works and Safety - Aug 11, 2026
WWTU Director Dave Henderson reported design drawings are nearing 100% and submitted to IDEM, with Bowen Engineering developing a guaranteed maximum price; a bond ordinance is coming to City Council soon.
City Council - Aug 3, 2026
New sewer connections will pay $2,500 to $400,000 depending on meter size, replacing the old flat $400 tap fee, with money going to infrastructure. Builders say they understand the need after staff meetings but worry about housing costs; the Indiana Apartment Association opposes it.
Pre-Council - Jul 30, 2026
New sewer connection fees ranging from $2,500 to $400,000 by meter size would replace the old tap fee and expired interceptor/lift station fees. The Builders Association is now on board, and it takes effect 180 days after adoption.
City Council - Jul 6, 2026
The city wants to replace its $400 sewer tap fee with a $2,500-per-home connection charge (scaling up to $400,000 for industrial meters) to fund future plant expansion without raising rates on existing customers. Builders say it's under-publicized, funds operations, and makes West Lafayette less affordable to build in.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for West Lafayette
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.