Trinitas Riverfront Development Timeline
Summary
The Trinitas project at River Road and Tapawingo slipped a year; the amended MOU sets closing for March 2027 and Phase 1 occupancy by end of 2029. The developer builds ~$18.8 million of public infrastructure and recoups half the project's TIF revenue over 25 years.
At a glance
- Total mentions
- 1
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 21, 2026.
Impact analysis
No change in the city's obligation; the incentive pays out only as the project generates tax revenue.
The development brings new riverfront mixed-use space plus stormwater detention, a raised Wood Street, and a trailhead connection off Tapawingo.