Building Commissioner Jason Hardebeck reported F.A. Wilhelm has scheduled six concrete pours for the Indiana FAB project in August, including one Saturday (Aug. 8), following last week's weekend-work concerns.
At a glance
- Total mentions
- 6
- Last 30 days
- 2
Discussed at 2 meetings in the last 60 days; most recently Nov 17, 2026.
Impact analysis
No direct city cost — fees pass through to the facility owner.
The Indiana FAB project advancing on schedule.
Nearby residents may experience early-morning construction activity, including on Saturday, August 8.
Mentions & discussions (6)
Board of Public Works and Safety - Nov 17, 2026
The city is lining up Bureau Veritas to do plan review and inspections at the giant SK hynix chip plant — a one-of-a-kind project needing specialized expertise. The fee gets passed through the city and fully paid by SK hynix, but the agreements weren't signed in time, delaying inspectors about two weeks.
Board of Public Works and Safety - Oct 27, 2026
Concrete pours for the Indiana FAB project are too large to fit within normal hours, so crews got a November suspension allowing 5-7 a.m. work on select weekdays. No weekend pours are planned.
Board of Public Works and Safety - Aug 4, 2026
Building Commissioner Jason Hardebeck reported F.A. Wilhelm has scheduled six concrete pours for the Indiana FAB project in August, including one Saturday (Aug. 8), following last week's weekend-work concerns.
Board of Public Works and Safety - Jun 30, 2026
Neighbors near the Indiana FAB project will hear construction starting at 5 a.m. throughout July — the city waived its noise ordinance so giant concrete pours can beat the summer heat.
Board of Public Works and Safety - Jun 16, 2026
The city is hiring an outside firm to handle specialized plan reviews and inspections for big developments — and the developer pays, not taxpayers. The lone bid's $4.99 million lump sum looks off, so the board is holding it for clarification.
Board of Public Works and Safety - May 26, 2026
The Building Department will hire an outside firm to handle plan review and inspections for the new semiconductor high-bandwidth memory packaging facility. The cost passes through to the facility owner, and the resulting records stay subject to Indiana public records law.
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for West Lafayette
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.