Twenty-three years of work has cut sewer overflows into the Wabash from 25.5 million gallons in one 1993 month to 91,000 gallons in all of 2025. A new LEED-certified lab building and wet weather basin are wrapping up, and upcoming treatment upgrades should largely avoid ratepayer bonding impacts.
At a glance
- Total mentions
- 2
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 10, 2026.
Impact analysis
Small inflationary utility rate adjustments (~2% per year over four years) are expected, but major upgrades should mostly avoid new rate impacts.
Everyone who lives near or recreates on the Wabash, plus ratepayers spared major bonding costs.
Mentions & discussions (2)
Board of Public Works and Safety - Nov 10, 2026
During heavy rains, brief sewer overflows happen at the Delhart Street weir because the CSO tunnel can't fill fast enough. A $10,000 Grundfos study will explore ways to push more stormwater into the tunnel — better river water quality for everyone.
City Council - Aug 3, 2026
Twenty-three years of work has cut sewer overflows into the Wabash from 25.5 million gallons in one 1993 month to 91,000 gallons in all of 2025. A new LEED-certified lab building and wet weather basin are wrapping up, and upcoming treatment upgrades should largely avoid ratepayer bonding impacts.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for West Lafayette
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.