Chauncey Avenue Concrete Replacement
Summary
Crews will rip out and replace the entire street surface curb to curb this summer, before students return, fixing concrete that wasn't repaired last year.
At a glance
- Total mentions
- 7
- Last 30 days
- 0
Last discussed Aug 19, 2026.
Impact analysis
Cost borne by Winco Construction under warranty.
Drivers, pedestrians and Purdue traffic on Chauncey get a smooth street before fall semester.
Pedestrians and library visitors face detours until August 21.
Mentions & discussions (7)
Redevelopment Commission - Aug 19, 2026
A $74,600 survey is the first step to separate the last combined storm/sanitary sewer section on Chauncey Avenue, reducing sewage overflows into the Wabash and avoiding digging twice during the South Street Plaza project.
Board of Public Works and Safety - Aug 18, 2026
The rebuilt roadway had durability problems because the original mix design was a pedestrian-landscape material, and the contractor is replacing it at its own cost. It reopened to foot traffic but needs weeks to cure before vehicles can return.
Board of Public Works and Safety - Jul 21, 2026
Sidewalks and crosswalks near the library and City Hall are closed until August 21 because Winco's road sealer failed — the contractor is rebuilding the entire drivable surface under warranty.
Redevelopment Commission - Jul 15, 2026
The concrete outside City Hall failed after recent replacement and is being redone at no cost to the city. The road should reopen by August 21, in time for Global Fest.
Board of Public Works and Safety - Jun 23, 2026
A stretch of Chauncey Avenue downtown will be closed to vehicles for nearly two months while the failing road is rebuilt with Class A concrete. Sidewalks stay open so people can still reach City Hall and the library on foot.
Redevelopment Commission - Jun 17, 2026
Chauncey in front of City Hall closes for a full curb-to-curb concrete rebuild starting late June, reopening around August 21. Meanwhile, new street lights on Robinson and Indian Trail should be live by late June and July.
Redevelopment Commission - May 20, 2026
Crews will rip out and replace the entire street surface curb to curb this summer, before students return, fixing concrete that wasn't repaired last year.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for West Lafayette
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.