Arbor Chase spillway project change order
Summary
The city is paying another $15,150 to fix the drainage channel between University Farm and Arbor Chase after earlier concrete work didn't meet standards.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 6, 2026.
Impact analysis
Adds $15,150 to the stormwater-funded contract, now totaling $110,150.
Homeowners in University Farm and Arbor Chase get a properly functioning drainage basin.
Mentions & discussions (2)
Board of Public Works and Safety - Oct 6, 2026
The city is paying another $15,150 to fix the drainage channel between University Farm and Arbor Chase after earlier concrete work didn't meet standards.
Board of Public Works and Safety - Aug 11, 2026
The spillway that runs under Kalberer Road from University Farms to the Arbor Chase pond needed unexpected soil replacement and a weather-delayed schedule, adding $14,314 to the contract (now $351,831), paid from stormwater funds.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for West Lafayette
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.