Meijer #186 Subdivision, Replat of Lot 6A Autozone #5535 Subdivision (S-5376)
Description
Developers seek to split 9.41 acres into four lots and develop three of them without dedicating 1.66 acres for the planned US 231/North 200 West realignment, calling the requirement an unconstitutional taking.
Impact summary
The Board of Public Works and Safety denied it on Oct 6, 2026.
How much land gets set aside for future US 231 widening shapes the road network around this US 52 commercial site.
Applicant
- Name
- MSquare Development and Gate Development
- Address
- 2568 US Highway 52 West, West Lafayette, IN 47906
At a glance
- Hearings
- 3
- Public comments
- 0
- Total mentions
- 3
Last vote · Board of Public Works and Safety
Discussed at 1 meeting in the last 60 days; most recently Oct 6, 2026.
Meeting timeline (3)
Board of Public Works and Safety - Oct 6, 2026
Developers want to split the 9.41-acre parcel into four lots and build three commercial lots on the west half, but asked the Board to waive dedicating 1.66 acres for a future North 200 West widening. The Board unanimously denied the variance.
Board of Public Works and Safety - Sep 15, 2026
Developers seek a variance from the USO's right-of-way dedication requirement so they can subdivide 9.4 acres into four lots without dedicating 1.66 acres for a future road widening, arguing it's an unconstitutional exaction. The board tabled the request up to 30 days.
Board of Public Works and Safety - Sep 8, 2026
Developers want a variance from the requirement to dedicate full right-of-way for a proposed arterial (US 231), seeking a 5-lot commercial subdivision on 9.41 acres. The Board continued the request to September 15 over unresolved questions.
Related issues (3)
We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.
The weekly brief for West Lafayette
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.