Fire Station 85 technology lease-to-own
Summary
The new Fire Station 85 project got a utility easement with Citizens Water and an owner's change order funded outside the city's bonds. Construction moves ahead with the developer right away.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Jul 22, 2026.
Impact analysis
The change order cost will be budgeted in next year's budget, outside the project's bond funding.
Residents on the growing northwest side get fire coverage from the new station sooner.
Mentions & discussions (2)
Board of Public Works - Jul 22, 2026
The new Fire Station 85 project got a utility easement with Citizens Water and an owner's change order funded outside the city's bonds. Construction moves ahead with the developer right away.
City Council - Jun 8, 2026
Instead of burying tech costs in a 20-30 year bond, the city will lease fire alarm, cameras, door access and AV systems over five years with maintenance included.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Westfield
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.