Built PUD Amendment One
Description
A concept-plan reconfiguration of the ~10.5-acre Built PUD, replacing two access drives with a public street through the site; uses and tree preservation commitments unchanged. (Not on the published agenda; taken up after the tree ordinance.)
Impact summary
The makerspace/office site near Gray Road and SR 32 gets a cleaner layout that can move forward to Council.
Applicant
- Address
- Southwest side of State Road 32 and Gray Road
At a glance
- Hearings
- 3
- Public comments
- 0
- Total mentions
- 3
Last vote · City Council
Last discussed Aug 10, 2026.
Meeting timeline (3)
City Council - Aug 10, 2026
A concept map amendment to the BUILT PUD replacing two drives with one public road crossing the pipeline- and easement-encumbered site. No changes to permitted uses.
Advisory Plan Commission - Aug 3, 2026
A 10.58-acre concept plan amendment reconfigures access to Republic Street to work around pipelines and a Duke transmission line; recommended favorably 7-0.
City Council - Jul 27, 2026
A concept-plan reconfiguration of the ~10.5-acre Built PUD, replacing two access drives with a public street through the site; uses and tree preservation commitments unchanged. (Not on the published agenda; taken up after the tree ordinance.)
We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.
The weekly brief for Westfield
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.