Judicial center roof replacement
The Judicial Center's roof is leaking and the county picked between two bids that differ by more than $56,000. The low bidder skipped turret repairs, so there's a follow-up question on fixing those leak-prone areas.
Hanging Rock Road bridge replacement (Bridge 96)
The board approved USI's contract to inspect construction of Bridge #96 over the Salamonie at Hanging Rock — a step toward completing a key local bridge project.
2027 JCAP grant funding
The probation department seeks the 2027 Justice Partners Nation's Response Grant, which brought the county roughly $404,388 last year for addiction-related services. Funding levels may be reduced, but the county will apply for the same amount.
Horse-drawn vehicle safety ordinance
The county's proposed registration and operational rules for horse-drawn vehicles and trailers got tabled again while commissioners hold more discussions, including a Friday meeting with county officials. Any new version will carry a 2026 ordinance number.
Proposed Greentown-Sorenson transmission line
Indiana Michigan Power's proposed route appears to run within the county's 1,320-foot setback from residential zones in several spots. The commissioners sent a formal letter demanding talks before any final route decision.
County bridge and highway funding pressures
Major bridge work is moving: the LaFontaine bridge redesign saves $200,000, the North Manchester Market Street bridge opens end of July, and 1100 North resurfacing finishes soon.
Road jurisdiction swap with City of Wabash
The city and county tried to tidy up who maintains segments of County Road 50 North and 100 West near the Ford Meter Box expansion — but residents pushed back hard on traffic, road condition, and hidden costs. The deal is tabled until the county council can review it and budget for repairs and matching funds.
Temporary moratorium on data center permits
Wabash County has zero zoning rules for data centers, so the county is pausing all such permits while it writes them. Concerns include water use, noise, environmental impacts, and fast-changing technology. A draft ordinance is already underway, with a goal of completion within a year.
Carbon sequestration ordinance
The board reviewed 68 letters from residents opposed to carbon capture and sequestration projects, alongside IDEM final decisions on local biofuel and recycling facilities.
America Road repairs and deferred acceptance
America Road reopened June 29 after the contractor fixed 36 spots of lime stabilization failure, but the county is holding off formally accepting the road so the contractor stays liable under its one-year maintenance term if problems resurface.
Carbon sequestration zoning ordinance amendment
A resident letter opposing carbon capture sequestration was reviewed by the commissioners. No action was taken on it this meeting.
ADA and Title VI compliance
Consultants warned the county faces wide-ranging ADA and Title VI requirements — from buildings and sidewalks to websites — with new federal website accessibility rules due in 2027 and billion-dollar lawsuits looming elsewhere. The county must plan to catch up, including choosing a cut-off date for making older documents accessible.
Bowen Health 2027 county funding request
Bowen Health is asking the county for $303,000 in 2027 funding. It served more than 4,300 Wabash County patients last fiscal year, up from about 2,957, and its new building will add therapists, dental care, and a public pharmacy. Commissioners haven't decided on the funding yet — it will factor into budget deliberations.
Health Department relocation and nursing transition
A $9,950 change order covers floor leveling, masonry upgrades, and leftover pipe cleanup for the Health Department project. Carpet could be installed by early March with move-in by end of the first quarter.
Zoning ordinance rewrite and weak code enforcement
The county is spending $20,000 to finish updating its zoning ordinance, but residents point out enforcement is complaint-based and 95% of variances get approved. Commissioners may seek funding for a part-time enforcement officer during budget talks.
POET Biorefining lawsuit defense
Commissioners reviewed 15 letters supporting and 15 opposing carbon capture and sequestration, plus two IDEM permit applications — no action was taken.
Flood Damage Prevention Ordinance 2026-85-02
This FEMA-required update keeps the county in good standing with federal flood programs. It mostly involves definition changes and was already approved by the towns of Lagro, Roann, and LaFontaine plus the Plan Commission.
Kettelhut jail roofing settlement
The general contractor for the new jail filed a claim against the county, and it heads to mediation Thursday. Niccum got authority to settle for up to $125,000 — the amount the county has been holding back from the contractor.
Jail maintenance costs mounting
Rain and snow are getting into the jail's roof vents, forcing a $29,147.76 repair with only one bid for each piece. Commissioners worry the jail's maintenance budget — cut from $50,000 to $40,000 — is too small and more repairs are coming.
Daniel's Place construction contract
Hamilton Hunter of Fort Wayne is the low bidder at $2.7 million for the Daniel's Place project. Construction could start demolition within weeks, with completion expected in 2026.
Transit driver shortage cuts service
Living Well of Wabash County transit is down to four days a week after a driver's sudden illness, and recruiting is tough because state fitness-for-duty rules disqualify many applicants. Starting pay was raised to $15 an hour.
Winter road conditions and snow removal strategy
Residents flooded the county with calls over drifting roads, and the highway superintendent was out plowing rather than attending. Officials explained that plowing during blowing snow is wasted effort — roads close right back up — so crews waited for the wind to die down.
Tax Abatement Rejection
Wabash County officials rejected a tax abatement for Owens Corning Thermafiber, so the company won’t get a property tax break on its local operations. It’s a straightforward tradeoff: the city keeps more tax revenue, but the company faces a higher local tax bill. The decision signals how aggressively the city is willing to use incentives to attract or retain business.