Bridge 143 and 700 West projects
The highway department is putting its yearly materials and equipment bids out for the December 7 opening, and work on Bridge 143 east of Treaty is moving ahead without delays.
Hanging Rock Road bridge replacement (Bridge 96)
The board approved USI's contract to inspect construction of Bridge #96 over the Salamonie at Hanging Rock — a step toward completing a key local bridge project.
Community Crossings projects complete
The county signed the Community Crossings matching grant construction contract, reviewed by counsel and INDOT, moving local road projects forward.
Market Street Bridge completion
The North Manchester Market Street Bridge, opened Labor Day weekend, finished $95,763 under budget at $3.59 million. Final acceptance runs to July 2027 pending Purdue core-drill results.
County Road 100 West / industrial park traffic
The city wants the county to take back 100 West for industrial park traffic; a resident says old bylaws required traffic to exit via Ringle Avenue to SR 13 and wants the board to find those bylaws.
Road jurisdiction swap with City of Wabash
The city and county tried to tidy up who maintains segments of County Road 50 North and 100 West near the Ford Meter Box expansion — but residents pushed back hard on traffic, road condition, and hidden costs. The deal is tabled until the county council can review it and budget for repairs and matching funds.
North Manchester bridge delay
The Market Street bridge in North Manchester is on time and on budget and expected to open on or about July 15, restoring a key crossing.
America Road repairs and deferred acceptance
America Road reopened June 29 after the contractor fixed 36 spots of lime stabilization failure, but the county is holding off formally accepting the road so the contractor stays liable under its one-year maintenance term if problems resurface.
Community Crossings small structure replacements
The county opened bids to replace three small structures. Bercot's $955,687 bid is about $72,000 lower than Pioneer's, but the board hasn't awarded the contract yet.
State Road 16 resurfacing detour plan
INDOT plans to resurface State Road 13 to the Huntington County line in spring 2027 in three phases, and the commissioners signed the detour plan. Expect detours when construction starts.
Bridge #196 engineering scoring
Highway Superintendent Ryan Smith said engineering firms for Bridge #196 construction inspection will be scored after the commissioners return from the NACO conference.
Transit driver shortage cuts service
Living Well of Wabash County transit is down to four days a week after a driver's sudden illness, and recruiting is tough because state fitness-for-duty rules disqualify many applicants. Starting pay was raised to $15 an hour.
Winter road conditions and snow removal strategy
Residents flooded the county with calls over drifting roads, and the highway superintendent was out plowing rather than attending. Officials explained that plowing during blowing snow is wasted effort — roads close right back up — so crews waited for the wind to die down.
Bridge 143 construction moving forward
Bridge 143 on 1050 South went out for bid and the contract was awarded to Millstone Construction; the one-lane condition in Manchester has been manageable so far.