Poet Square detention basin dispute
Summary
The apartment project's final drainage plan was approved, but underneath it is a bigger problem: the subdivision's detention basin was built wrong years ago and holds only 56% of its design volume. Officials worry about flooding over Peck Road and are weighing who pays to fix a basin the apartment developer barely touches.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Mar 31, 2026.
Impact analysis
Fixing the basin could mean doubling the lake's size or lowering the outlet pipe — costs unresolved.
The apartment developer, whose project can proceed without fixing the basin.
Homeowners near the basin and along Peck Road face higher flood risk from the under-sized basin.
Mentions & discussions (1)
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Vanderburgh County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.