Fieldstone I failing streets

Summary

The original developer is gone, the roads are failing, and the new developer offered to fix them now if the county accepts them even without every punch-list item met. The county chose the deal over waiting three years on a shrinking letter of credit.

At a glance

Total mentions
3
Last 30 days
1

Discussed at 1 meeting in the last 60 days; most recently Oct 27, 2026.