County Road Resurfacing and Oak Hill Reconstruction Change Orders
Summary
Two contract changes add about $68,400: extra asphalt to fix low spots and drainage on resurfaced county roads, and removal of a large tree threatened by new sewer work on Oak Hill Road.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 13, 2026.
Impact analysis
About $68,400 in combined contract increases to county road projects.
Drivers on resurfaced county roads and the Oak Hill Road neighbor spared a falling-tree hazard.
Mentions & discussions (4)
Board of County Commissioners & Drainage Board - Oct 13, 2026
Two contract changes add about $68,400: extra asphalt to fix low spots and drainage on resurfaced county roads, and removal of a large tree threatened by new sewer work on Oak Hill Road.
Board of County Commissioners & Drainage Board - Jun 30, 2026
Traffic detouring around the Oak Hill Road project is creating speeding problems on Clover Drive, prompting a temporary 15 mph limit. The project also got a 22-day no-cost extension for drainage design fixes.
Board of County Commissioners (No Drainage Board) - May 26, 2026
E&B Paving's $558,222.99 contract targets roads untouched in years, some never repaved since construction, including University Parkway interchange ramps.
Board of County Commissioners & Drainage Board - Jan 27, 2026
Three bids for this year's county road milling and resurfacing came in between $1.44 million and $1.65 million, with the county expecting up to $1 million back through the Community Crossings program.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Vanderburgh County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.