Civic Issues
Topics getting the most attention in Valparaiso public meetings, ranked by how frequently they are discussed.
3 issues in water utilities with medium priority
Utilities infrastructure projects
Big sewer separation and water main work coming to Franklin Street, plus a lead service line replacement project backed by $2.5 million in grant and $2.5 million in 0% loan money.
Franklin Street Improvements (2027)
Water main, storm sewer, and road work on Franklin Street will be combined into one project totaling about $1.9 million. Bids open November 10.
Weston Street storm sewer separation
A $2.2 million project to install 1,200 feet of new storm sewer downtown, cut Salt Creek overflows, and reduce basement backups and street flooding — partially paid by a $959,000 EPA grant.