Midwood Terrace Phase 2 performance bonds
Summary
The next phase of Midwood Terrace is moving forward with 8 new single-family lots and a townhome section of 88 lots. A separate plat sets aside about 2 acres for Fire Station No. 4 so the land can transfer to the Fire Territory.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 9, 2026.
Impact analysis
The performance guarantee for the development was already approved at a prior meeting; no new cost was discussed.
Future Midwood Terrace residents gain new housing, and the Fire Territory gains its station site.
Mentions & discussions (2)
Board of Works - Oct 9, 2026
The next phase of Midwood Terrace is moving forward with 8 new single-family lots and a townhome section of 88 lots. A separate plat sets aside about 2 acres for Fire Station No. 4 so the land can transfer to the Fire Territory.
Board of Works - Aug 28, 2026
The board accepted nearly $850,000 in performance bonds from Olthof Homes, guaranteeing the subdivision's roads, sidewalks and storm sewer get built properly before the bonds are released.
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Valparaiso
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.