Park Avenue lift station and 13th Street overpass projects
Summary
The city's sewer system serves areas beyond city limits, and the Park Avenue lift station — 30 feet deep with a high water table — needs replacing after a nearby force main corroded and discharged sewage. The $4.5 million appropriation completes a project in the long-term control plan.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Apr 2, 2026.
Impact analysis
$4.5 million redirected from the wastewater treatment plant fund, part of an estimated $330 million in sewer projects over 25 years.
Residents north of Park Avenue across the sanitary district get a reliable sewer system and fewer sewage-discharge risks.
Residents displaced by overpass demolition lost their homes, though the city is handling relocations.
Mentions & discussions (3)
City Council Video — 2026-04-02
The city's sewer system serves areas beyond city limits, and the Park Avenue lift station — 30 feet deep with a high water table — needs replacing after a nearby force main corroded and discharged sewage. The $4.5 million appropriation completes a project in the long-term control plan.
City Council Video — 2026-03-05
The overpass demolition at 13th and 8th Avenue has cleared six houses and three garages, with construction bid expected around August 2027. The Park Avenue main lift station came in $1.1 million under budget at about $5.3 million, and 90% of the work may be done this year using last year's unspent appropriation.
City Council Video — 2026-02-05
Demolition of 24 homes clears the way for utility moves on the long-awaited overpass, saving about $130,000 by using city staff, while a federal utility study grant advances for the 181st wing.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Terre Haute
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.