Poka-Bache South Phase 1 right-of-way and condemnation
Summary
The county paid its $3,065 annual trail dues and signed a letter of support for Allen County's grant application — the trail is coming in under budget, which might free up more money.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Jul 7, 2026.
Impact analysis
$3,065 annual dues funded from the same source as 2025.
Trail users and communities along the Poka-Bache route.
The Parcel 5 owner, who receives an appraisal-based price rather than their asking amount.
Mentions & discussions (3)
Board of Commissioners — July 7, 2026
The highway project hit a snag when a property owner rejected the county's maximum lawful offer for Parcel 5, so commissioners authorized condemnation — the owner will get the average of three court appraisals. The recording also captures a spoken dissent at the vote that the minutes record as unanimous.
Board of Commissioners — April 7, 2026
The roundabout at 100 N/200 W is waiting on utility relocations, Bridge 37 right-of-way work starts this July, and the Poka-Bache South trail shifted onto Collen Street. A $185,451 Mint City contract clears right-of-way along Old 27, and Angola will keep mowing and plowing the north trail section for $18,000 a year.
Board of Commissioners — January 20, 2026
The county paid its $3,065 annual trail dues and signed a letter of support for Allen County's grant application — the trail is coming in under budget, which might free up more money.
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Steuben County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.